RAMS for general builders
A general builder's job covers many trades, so the RAMS covers more hazards than most: access, dust, noise, asbestos, deliveries and working around the people who live there.
General builder preset: 16 hazards with controls, 9 steps of work, PPE and plant, ready to edit and download as a PDF.
Make RAMS for general buildersHazards and controls
These are the hazards the general builder preset starts with. Residual risk is after the controls, on a 5 × 5 likelihood and severity scale.
Falls from ladders or stepladders
Work at height: ladders and stepladders · Who: Operatives · Residual risk: Medium
- Ladders used only for short-duration (up to 30 minutes in one position), light work where a tower or podium is not reasonably practicable
- Professional ladders to BS EN 131, checked before use (stiles, feet, rungs, locking bars) and taken out of use if damaged
- Ladder set at 1 in 4, on firm level ground, tied or footed; extends 1 m above the landing point
- Three points of contact kept; no overreaching, belt buckle stays inside the stiles
- No work from the top three rungs of a ladder or the top two treads of a stepladder
Tools or materials falling from height
Work at height: ladders and stepladders · Who: Operatives, client, public · Residual risk: Low
- Area below kept clear or coned off
- Tools carried in a belt or pouch, not in the hands while climbing
- Nothing left on top of stepladders
Falls from the working platform
Work at height: mobile access towers and podiums · Who: Operatives · Residual risk: Medium
- Tower erected, altered and dismantled by a PASMA-trained person following the manufacturer's instructions
- Guardrails and toe boards fitted on every working platform
- Tower inspected before first use, after alteration and after any event that could affect it; inspection recorded
Tower overturning or collapsing
Work at height: mobile access towers and podiums · Who: Operatives, others nearby · Residual risk: Medium
- Castors locked and outriggers or stabilisers fitted; base on firm, level ground
- Tower never moved with people or materials on it
- Safe working load and height-to-base ratio not exceeded; no ladders or steps used on the platform
- Not used in high winds or near overhead power lines
Cuts, entanglement and flying particles from tools
Hand and power tools · Who: Operatives, others nearby · Residual risk: Medium
- Tools suitable for the task, maintained, with guards fitted
- Only trained and competent people use powered tools
- Blades and discs changed with the tool unplugged or battery removed
- Eye protection worn when cutting, drilling or grinding
Electric shock from tools and leads
Hand and power tools · Who: Operatives · Residual risk: Medium
- 110 V (centre-tapped) or battery tools on site; leads checked before use
- Portable equipment inspected and tested at suitable intervals
- Leads routed away from water and sharp edges
Back and muscle injuries from lifting and carrying
Manual handling · Who: Operatives · Residual risk: Medium
- Loads assessed before lifting; mechanical aids (trolleys, sack trucks, hoists) used where possible
- Heavy or awkward loads lifted by two people
- Loads broken down into smaller units; materials delivered close to where they are needed
- Operatives shown good lifting technique
Breathing in silica dust (lung disease)
Dust: cutting, chasing and drilling masonry and concrete · Who: Operatives, client, others nearby · Residual risk: Medium
- Tools with on-tool extraction to an M- or H-class vacuum, or water suppression
- FFP3 mask, face-fit tested, worn as well as extraction
- Work area closed off and ventilated; others kept away
- Dust cleaned with an M-class vacuum, never by dry sweeping or compressed air
Hearing damage from noisy tools
Noise and hand-arm vibration · Who: Operatives, others nearby · Residual risk: Medium
- Quieter tools and methods chosen
- Hearing protection worn where noise is above 85 dB(A) or people must shout to be heard 2 m away
- Others kept away from noisy work
Hand-arm vibration (HAVS, white finger)
Noise and hand-arm vibration · Who: Operatives · Residual risk: Medium
- Low-vibration tools chosen and maintained
- Trigger time limited using the tool's vibration level and the HSE exposure points system
- Tasks rotated; breaks taken; hands kept warm
- Symptoms reported; health surveillance where exposure is regular
Disturbing asbestos in buildings built before 2000 (lung disease)
Asbestos · Who: Operatives, client, occupants · Residual risk: Medium
- Client asked for the asbestos register or survey before work; a refurbishment survey where work is intrusive
- Operatives have asbestos awareness training
- If suspected asbestos is found: stop work, keep people out of the area, tell the client and do not restart until it has been tested
- Licensed work only by a licensed contractor
Striking hidden cables, pipes or gas mains when drilling, cutting or digging
Hidden and buried services · Who: Operatives, client · Residual risk: Medium
- Service drawings and client information checked before work
- Walls and floors scanned with a cable and pipe detector; buried services traced with a CAT and Genny
- Hand-dug trial holes before machine digging near services
- Water and gas located and the stopcock or ECV position confirmed before starting
Skin, eye or breathing harm from adhesives, sealants, solvents, cement and cleaning products
Hazardous substances (COSHH) · Who: Operatives, client · Residual risk: Medium
- Safety data sheets and COSHH assessments available for products used
- Less harmful products chosen where possible
- Gloves, eye protection and good ventilation as the data sheet says
- Wet cement and lime kept off skin; washing facilities used before eating
- Products stored in their original containers, lids on, away from children
Injury to the client, children, pets or the public
Working in occupied homes and premises · Who: Client, occupants, public · Residual risk: Low
- Work area agreed with the client and closed off with barriers or doors
- Tools, materials and chemicals never left unattended in reach of children
- Access routes and fire escape routes kept clear
- Occupants told about noisy, dusty or disruptive work in advance
- Services only isolated after warning the occupants
Slips, trips and falls on the same level
Slips, trips and housekeeping · Who: Operatives, client, public · Residual risk: Low
- Work area kept tidy as work goes on; waste cleared at least daily
- Leads and hoses routed away from walkways or covered
- Good lighting on access routes; spills cleaned at once
- Floor protection taped down at the edges
Being struck by vehicles reversing or delivering
Deliveries and vehicles on site · Who: Operatives, public · Residual risk: Medium
- Deliveries planned and booked; unloading area agreed
- Banksman used for reversing; pedestrians kept apart from vehicles
- Hi-vis worn in vehicle areas
Sequence of work
- Agree the programme, access, deliveries, welfare and working hours with the client
- Check the asbestos survey and the service drawings before any demolition, drilling or digging
- Set up the site: barriers, signage, skip, welfare and storage
- Plan work at height; erect towers or arrange scaffold before high-level work
- Carry out strip-out and building work in the planned sequence with dust and noise control
- Coordinate other trades; brief everyone on the RAMS and site rules
- Inspect access equipment, excavations and temporary works as required
- Clean the site daily and remove waste
- Snag, clean and hand over to the client
PPE
Safety boots, Hi-vis vest, Hard hat, Eye protection, Gloves, Hearing protection, FFP3 dust mask (face-fit tested).
Plant and equipment
- Mobile tower or scaffold
- Ladders and stepladders (BS EN 131)
- 110 V or battery power tools with dust extraction
- Disc cutter with water suppression
- Cable and pipe detector
- Skip and site barriers
Every job is different: delete what does not apply, add site-specific hazards and name the people responsible before you issue the RAMS.
Questions
Do I need a construction phase plan as well?
Under CDM 2015 every construction project needs one, including domestic jobs. RAMS Maker has a separate construction phase plan generator.
Who prepares RAMS on a job with subcontractors?
Each contractor prepares RAMS for their own work. The principal contractor checks they fit together and coordinates the site.
Other trades: Roofers · Plumbers and heating engineers · Painters and decorators · Carpenters and joiners · Plasterers and dryliners · all trades
Related: RAMS template · Method statement template · Toolbox talks